Slate roofing installation: step-by-step instructions from preparation to finish
Slate installation is the process of laying asbestos-cement corrugated sheets on a pitched roof. Key stages: preparing the lathing at a pitch of 500–600 mm, cutting and drilling the sheets, laying them staggered with a longitudinal overlap of 120–200 mm and a transverse overlap of 1–2 waves, fastening with slate nails into the upper wave. The tightness and durability of the roof depend on the precision of each step.
What you need to know before installing slate
How to lay slate is a common question, so let us look at it in detail. Before starting to install slate, it is important to assess the roof structure, choose a suitable material and understand how the slope affects the laying technology. Let us go through the basic parameters.
Which slate to choose: 7--wave or 8--wave?
| Parameter | 7--wave slate | 8--wave slate |
|---|---|---|
| Sheet length | 1,75 m | 1,75 m |
| Sheet width | 0,98 m | 1,13 m |
| Thickness | 5,2 mm | 5,8 mm |
| Sheet weight | ~23 kg | ~26 kg |
| Number of waves | 7 | 8 |
| Consumption per 10 m² | ~5,8 sheet | ~5,1 sheet |
Minimum roof pitch for slate
The minimum pitch when installing slate is 12°, with the longitudinal overlap increased to 200 mm and the transverse one to 2 waves. On slopes of 15–20° the standard longitudinal overlap is 120 mm with an overlap of 1 wave, while on steep roofs from 25° it can be reduced to 100 mm. At a pitch of 12–14° each sheet of the upper row must overlap the lower one by 200 mm — this compensates for the slower drainage of water on a shallow surface. Even on a slope of 15° with a quality profile, we recommend an overlap of at least 150 mm to prevent slanting rain from being blown into the joints. On roofs with a pitch of less than 12° slate is not recommended — water will stagnate in the waves, leading to leaks and destruction of the material.
How to calculate the number of slate sheets for a roof
To calculate the number of sheets, divide the roof slope area by the usable area of one sheet (taking the overlap into account) and add 10% for cutting. The usable area of a 8--wave sheet with an overlap of 1 wave and 120 mm of longitudinal overlap is about 1,6 m², not the full 1,98 m² — this difference is often overlooked by DIY builders who order material to the exact measurement. For a 7--wave sheet under the same conditions, the usable area is about 1,3 m² against the full 1,715 m². On a gable roof of 8×10 m with a slope of 20° and gable overhangs of 0,5 m each, the area of one slope is 54 m²; divide by 1,6 m² and multiply by 2 slopes: we get 67,5 sheets, with a reserve of 10% — 75 sheets. The weight of such a batch is almost 2 tonnes (75 × 26 kg), so plan delivery and lifting onto the roof with the load-bearing capacity of the floors in mind.
Batten under slate: calculation and construction
Laying slate on a roof is a common question, so let us examine it in detail. The batten is the base on which the slate rests. How tightly the sheets lie and whether the roof will go wavy depends on its spacing and evenness.
What batten spacing is required for slate
The batten spacing for standard slate is 500–600 mm, and the distance is measured between the centres of the battens, not between their edges. For a 7-wave sheet 1750 mm long, a spacing of 500 mm gives support on three battens with spans of 500–500–500–250 mm; for a 8-wave sheet of the same length a spacing of 530–550 mm provides three supports with even load distribution. If the roof slope is less than 15°, it is better to reduce the spacing to 450–500 mm to compensate for the snow load — in the foothills of Almaty (Medeu district, Kamenka) this is especially relevant due to heavy precipitation. On flat roofs with a slope of up to 10° the batten spacing is reduced to 400 mm, otherwise the slate may crack under the weight of snow. Before marking, check the length of the sheet with a tape measure — different batches from the same manufacturer allow a deviation of up to 5 mm, and this shifts the support points.
What timber to make the batten from
For battens under slate, a timber batten with a cross-section of 50×50 mm from softwood with a moisture content of no more than 20% is used. A 40×50 mm batten is acceptable only on roofs with light snow loading — for regions with heavy precipitation it is better to take 50×60 mm. In Almaty, where the snow load in mountainous areas reaches 200 kg/m², a cross-section of 50×50 mm is the minimum workable option, and on slopes longer than 6 metres we recommend 60×60 mm. A 40×150 mm board is used for solid battens under the ridge and in valleys, but for the main field it is excessive and expensive. All battens are treated with a deep-penetration antiseptic before installation — on a slate roof the wood dries slowly, and without protection rot appears within 2-3 seasons.
Can slate be laid on an old batten
Slate can be laid on an old batten only after inspecting it: replacing rotten battens, checking the spacing and levelling the plane. Unscrew 2-3 sheets of the old slate in different areas of the slope and inspect each batten — if the wood crumbles under the pressure of an awl or is affected by mould, replace the entire section. Measure the spacing between the centres of the battens: the permissible deviation is 10 mm from the design value, otherwise the joint of the sheets will not coincide with the support. Check plane differences with a straightedge 2 metres long — the gap beneath it must not exceed 10 mm, otherwise the slate will lie in a wave and crack at the first heating in the sun. If the old batten has a spacing of more than 600 mm or differences of more than 10 mm per 2 metres, it is easier to dismantle it and make a new one — the time saved will turn into cracks in the slate.
Is waterproofing needed under slate
On a cold roof, waterproofing under the slate is not mandatory, but on an insulated (mansard) one it is mandatory, with a ventilation gap of 20–30 mm. For a cold roof it is enough to lay a strip of roofing felt under the bottom row of slate — this will protect the fascia board from running moisture. In a mansard, a vapour-permeable membrane (diffusion) is used, fastened from the bottom up with an overlap of 150 mm and the joints sealed with butyl rubber tape. The ventilation gap between the membrane and the lathing is provided by counter-battens of 30×50 mm timber — without it condensate will not be removed, and the wood will begin to rot within one winter. Even on a cold roof, waterproofing extends the service life of the lathing — condensate forming on the underside of the slate does not reach the wood.
Slate laying methods and overlap
Fastening slate on a roof is a common question, so let us examine it in detail. There are two main schemes for laying slate — staggered and with an offset. The choice depends on the roof pitch and the craftsman's personal preference. Let us examine both technologies.
Staggered laying: step-by-step diagram
Staggered laying is installation with each second row offset by half a sheet, which eliminates coinciding vertical joints. The first sheet of the bottom row is laid whole, the second row starts with a half sheet — this achieves bond of the seams and even distribution of the load from snow and wind. The longitudinal overlap between rows is maintained at 120–200 mm, the transverse overlap onto adjacent sheets is 1–2 waves depending on the slope. In practice we started the bottom row with a whole sheet, and the second with a half, having first cut the sheet along the wave with an angle grinder with a diamond disc. The staggered pattern is more often used on slopes up to 25°, where the load is distributed more predictably — on steep roofs an offset by half a sheet can give excessive material consumption without a noticeable gain in rigidity.
Offset laying: when and how to use it
Offset laying is a method in which each subsequent row is shifted by one wave relative to the previous one, rather than by half a sheet. The first row starts with a whole sheet, the second with an offset of one wave (about 150 mm for 8-wave slate), the third by another one, and so on until the full cycle. This approach is especially convenient on roofs of complex shape — mansard ones, with valleys or dormer windows, where cutting sheets is unavoidable. In our practice, on a gable mansard with two valleys, the offset by a wave allowed each sheet to be fitted individually without excess waste, whereas with staggered laying half the batch would have had to be cut. Offset by a wave requires careful marking of each row before fastening — an error in the shift of 10 mm accumulates and by the fifth row the discrepancy reaches 50 mm, which breaks the geometry of the roof.
What overlap should there be when laying slate
| Roof pitch | Longitudinal overlap | Lateral overlap |
|---|---|---|
| 12–15° | 200 mm | 2 waves |
| 15–25° | 150–180 mm | 1,5–2 waves |
| 25–30° | 120–150 mm | 1–1,5 waves |
| More than 30° | 120 mm | 1 wave |
The longitudinal overlap of slate is 120–200 mm, the transverse one 1–2 waves, and the exact values depend on the roof pitch. On shallow roofs (12–15°) the overlap is made as large as possible — 200 mm and 2 waves; on steep ones (from 30°) it can be reduced to 120 mm and 1 wave, saving material. At the same time, in the foothills around Almaty (the Kamienka and Gorny Gigant districts) we do not recommend reducing the longitudinal overlap below 150 mm even on steep slopes — wind from the mountains blows precipitation under the sheet, and the minimal overlap causes a leak in the second season.
How to trim slate corners when laying
The corners of the slate are cut diagonally by 30–50 mm on both sides of the sheet so that no thickening of 4 layers forms at the overlap points. Without such trimming, four layers at the points where the longitudinal and transverse overlaps intersect create unevenness under which water seeps. The corners are cut only on those sheets that meet in four-layer zones — usually the second and third rows; the bottom row and the ridge sheets are not trimmed, since at most two layers meet there. It is more convenient to cut with an angle grinder with a diamond disc for concrete, having first wetted the cutting line with water — this way asbestos dust does not fly, and the cut comes out clean, without chips that weaken the edge and lead to cracks during fastening.
How to drill and fix slate without mistakes
Drilling and fastening slate are the most critical stages. A mistake here leads to cracks, leaks and the need to redo the entire roof. I will explain how to avoid this.
How to drill slate so it does not crack
Drilling slate must be done from the back side of the sheet with a drill bit with a carbide tip 6–8 mm in diameter at low drill speed, without pressure. The idle speed is set to 400–600 per minute — on an ordinary household drill this is roughly one third of the trigger pressure. The drill bit enters the asbestos-cement mass softly, without jerking; the main thing is not to press with the body: the weight of the tool is sufficient. If you drill from the front side, the enamel chips around the hole, and at that spot the slate cracks when the nail is driven in. Before drilling, the hole location can be moistened with water — this reduces heating and the risk of cracking. The hole diameter should be 2–3 mm larger than the nail diameter so that during temperature expansion the fastener does not split the sheet.
What nails are needed for fixing slate
Special slate nails 80–100 mm long with a galvanised washer and a rubber gasket are used to fasten slate. The length is chosen so that the nail passes through the slate and the batten and enters the timber by 15–20 mm — for a batten of 50 mm board, a 80- mm nail is sufficient. A washer 12–16 mm in diameter covers the hole, and the rubber gasket beneath it, compressing, seals the joint. Ordinary construction nails without a washer and gasket must not be used — they do not seal the hole, and water will get under the slate, causing corrosion of the fasteners. In local building hypermarkets (Bely Veter, Price) slate nails are sold in packs of 1 kg — this is enough for approximately 10 sheets with the standard fastening pattern.
Which wave to drive nails into
Nails are driven into the top wave of the slate — this prevents water from entering the hole and ensures a watertight fastening. When fastened into the top wave, water runs down the crest without lingering at the nail head. According to the standards, 8–10 nails are used per sheet: four along the bottom edge (into the second and fourth waves), two along the top (into the first and fifth) and two to four in the middle with a spacing of 400–500 mm. Driving nails into the bottom wave is a gross mistake: water will run straight into the hole, and as the batten timber shrinks the slate may crack. Our crews on sites in Almaty use a 300–400 g hammer for driving — a heavy hammer strikes with recoil and splits the slate.
What to do if slate cracks during installation
If the slate cracks during installation, the sheet must be replaced — the crack will widen over time due to temperature deformation and will lead to a leak. A crack 10–15 cm long can grow to half a metre in a single season, especially on the south side of the roof, where temperature fluctuations are greatest. A temporary repair of the crack is possible with bitumen mastic and glass fabric, but this is a solution for 1–2 seasons. For a durable roof, the cracked sheet is replaced entirely. To avoid cracks, do not drive the nails all the way in — leave a gap of 1–2 mm between the head and the slate, otherwise when the battens settle the fastener tears out a piece of the sheet. Better to make an extra hole than to risk the integrity of the covering.
Details: ridge, junctions, eaves
The ridge, the wall abutments and the cornice overhangs are the most vulnerable points of a slate roof. Correct construction of these junctions guarantees the roof's tightness and durability.
How to fix slate on the ridge
The roof ridge is closed with a galvanised ridge element (ridge strip), which is fastened to the lathing through the upper wave of the slate. The standard length of the strip is 2 metres, and it is laid with an overlap of 100–150 mm from the lower edge to the upper one so that the joint is not blown through by wind. Fastening is done with metal self-tapping screws 50–70 mm long with a rubber gasket — two screws per wave on each side of the slope. A seal must be laid under the ridge strip: a special profiled one (matching the slate wave) or a universal foamed one on a self-adhesive base. In regions with strong winds, such as the foothills around Almaty, the ridge is additionally secured with wind strips at the edges. Before installing the ridge, the upper gap between the slopes is filled with expanding foam or insulation — this prevents snow from blowing in and condensation forming in the attic.
Construction of the eave overhang and drip edge
The cornice overhang of slate should project beyond the edge of the battens by 50–70 mm, and beneath it a drip cap is installed to drain condensate. The drip cap is a galvanised L-shaped strip mounted on the fascia board or the first batten of the lathing, projecting 20–30 mm beyond the edge of the overhang. It is fastened with galvanised nails or self-tapping screws at a pitch of 300–400 mm. If the drip cap is neglected, moisture from the inner side of the slate will run down onto the fascia board and the lathing, causing rot even in dry weather outside. For ventilation of the under-slate space in the cornice zone, a gap of 20–30 mm is left, covered with a perforated soffit strip — this prevents the lathing from rotting and extends the roof's service life by 5–7 years.
Slate junction to a wall or pipe
The abutment of slate to a wall or chimney is sealed with an apron of galvanised steel and bitumen tape led into a groove in the wall. The upper strip of the apron (wall profile) is led into a groove 20–30 mm deep, cut with an angle grinder along the joint line. The lower strip is laid over the slate with an overlap of at least 200 mm. The two strips are joined to each other with a lock or glued with bitumen tape. The point where the pipe enters is additionally reinforced: a hole is cut in the slate with a margin of 15–20 mm around the perimeter, and the gap is filled with silicone- or bitumen-based sealant. The height to which the apron is led onto the wall must be at least 150 mm, and the overlap onto the slate at least 200 mm. After the apron is installed, the groove is filled with cement mortar — this prevents water from getting behind the apron in slanting rain.
Is waterproofing needed under slate on a cold roof
On a cold roof, waterproofing under the slate is not mandatory but is desirable — it protects the lathing from condensate and extends the roof's service life. If the attic is unoccupied and well ventilated through dormer windows and cornice vents, waterproofing can be omitted. But on mansard roofs a waterproofing membrane is mandatory, with a ventilation gap of 20–30 mm between the membrane and the slate. For cold attics in the Almaty climate with temperature swings of up to 30°C between day and night, we recommend laying at least cheap roofing felt or tar paper — it costs pennies but saves the lathing from dampness in the wet shoulder seasons.
Common mistakes when installing slate
Even experienced craftsmen sometimes make mistakes. I have put together the five most common ones — check whether you are repeating them.
Mistake 1: fastening into the bottom wave
Fastening into the lower wave is the most common mistake: water seeps into the hole, and when the lathing shrinks the sheet cracks. The upper wave, on the contrary, acts as a natural canopy — even if the rubber washer eventually loses its seal, moisture simply runs down the crest without getting inside. For fastening we use galvanised slate nails 80–100 mm with a rubber gasket under the head — they secure the sheet without shattering the asbestos cement. The nail is driven strictly perpendicular to the plane of the sheet, without driving the head all the way home: a gap of 1–2 mm compensates for thermal expansion. Even if there is no leak at first, after 2–3 seasons the nail in the lower wave will begin to rust, and the slate around it will crumble. This can only be fixed by replacing the sheet.
Mistake 2: too large a batten spacing
A batten spacing of more than 600 mm causes the slate to sag under snow load and crack between the support points. For a standard sheet of 1750×1130 mm the optimal spacing is 500–530 mm: at such a distance each wave rests on a batten rather than sagging between them. On roofs with a slope of less than 12° the spacing is reduced to 450 mm to compensate for the increased snow load. We use 50×50 mm battens or 100×25 mm boards treated with preservative for the batten — in Almaty with its wet winters this is a mandatory condition. If the batten spacing exceeds 600 mm, the sheet works in bending rather than compression — for brittle asbestos cement this is critical. The normal spacing is 500–530 mm.
Mistake 3: failure to trim the corners
If the corners of the slate are not cut, a thickening of 4 layers forms at the overlaps, which prevents the sheets from fitting tightly against each other. When laying with an offset (staggered), we cut one corner of each sheet diagonally — on the side that rests on the wave below. For the non-offset pattern, we cut two corners so that the junction of four sheets at one point is flat. We do the cutting with an angle grinder with a diamond stone-cutting disc — be sure to wet the cut line with water to reduce asbestos dust and avoid chipping. Snow is blown and water seeps into the gap between sheets that do not fit tightly — over time this leads to rotting of the battens and leaks into the attic.
Mistake 4: drilling without a carbide-tipped drill bit
Drilling slate with an ordinary metal or wood drill causes overheating and cracking of the material — you need to use a drill with a carbide tip 6–8 mm in diameter. We drill the holes from the back of the sheet (the inner, matte side) — on the smooth front surface the drill slips and causes chipping. We make the hole diameter 2–3 mm larger than the nail diameter: the gap compensates for thermal expansion and prevents cracks when the lathing timber shrinks. We drill at low drill speeds, without strong pressure — asbestos cement cannot stand jerking. A carbide drill cuts the asbestos cement rather than shattering it. If you do not have such a drill to hand, you can use a tile drill — it gives a similar result.
Mistake 5: skimping on attic waterproofing
On a mansard roof, omitting waterproofing under the slate leads to the insulation getting wet, the rafters rotting and mould appearing. We use a diffusion membrane with a vapour permeability of at least 1000 g/m²/day — it releases moisture from the insulation to the outside but does not let condensate through from the inner side of the slate. The membrane is installed with a sag of 10–20 mm between the rafters so that condensate flows down rather than accumulating on the insulation. Between the membrane and the slate we leave a ventilation gap of 40–50 mm via the counter-battens — without it moisture will not evaporate. The waterproofing membrane in a mansard works in tandem with the ventilation gap: without the gap condensate will not evaporate, and the waterproofing becomes pointless.
Conclusion
We have covered the key stages of installing a slate roof: from the lathing to the fastening. Following the technology at every step guarantees the durability of the covering.
Key takeaways
Correct lathing at a pitch of 500–600 mm, accurate calculation of the overlap depending on the roof pitch, careful drilling from the back of the sheet and fastening into the upper wave — these are the foundations of a durable roof. Trimming the corners prevents leaks at the joints, and the use of galvanised self-tapping screws with a rubber gasket eliminates point corrosion. Slate is a fragile material, but if the technology is followed it lasts 30–50 years without repair. If you are unsure about any stage, it is better to consult an experienced roofer than to redo the whole roof a couple of seasons later.