To insulate an aerated concrete house correctly, choose vapour-permeable insulation — mineral wool with a density of 100–150 kg/m³. The layer thickness for Almaty is 100–150 mm with a 300–400 mm wall. The technology is a wet facade or a ventilated facade. Polystyrene foam is not recommended due to the risk of condensate and destruction of the aerated concrete.

Does a gas block house need insulation — criteria and rationale

The need for aerated concrete insulation — an aerated concrete house with a thermal imager on the facade, insulating an aerated concrete house

Insulating an aerated concrete house is a common question, so we will examine it in detail. We look at when aerated concrete needs insulation and when it can be done without. The key factors are wall thickness, density grade and climatic zone.

Do you need to insulate a gas block if the walls are 400 mm thick

Aerated concrete 400 mm thick of grade D500 has a thermal conductivity of about 0,14 W/(m·K), which gives a heat transfer resistance of roughly 2,86 m²·°C/W — this is insufficient for the climate of Almaty, where the SP 50.13330 standard requires 3,5–3,7 m²·°C/W. The gap of 0,64–0,84 units means that in winter the wall will freeze right through, shifting the dew point into the structure. In local conditions with a design temperature of −28°C and high air humidity (especially in the districts at the foot of the mountains, such as Kamenka or Gorny Gigant), an uninsulated 400 mm wall of D500 accumulates moisture up to 6–8% by mass in a single heating season — this is 2–3 times above the safe threshold of 3%. Even with a 500 mm wall of D400, heat losses through the building envelope account for 30–40% of the total — insulation reduces heating costs by 1,5–2 times, paying for itself within 3–5 heating seasons.

What the need for gas block insulation depends on

The need for aerated concrete insulation is determined by three factors: wall thickness (200–500 mm), density grade (D400–D600) and climatic zone — for Almaty with a design temperature of −25…−30°C, insulation is mandatory for any wall thickness up to 500 mm. For example, a D500 wall 300 mm thick without insulation gives a heat transfer resistance of about 2,14 m²·°C/W — that is 58% of the SP 50.13330 standard. At the same time, D400 blocks, although warmer due to greater porosity, are mechanically weaker and require masonry reinforcement every 3–4 courses, which increases the cost of the shell. In densely built-up areas (Zhetysu, Bostandyk), the wind load on the facade is higher — through uninsulated walls, wind penetration increases heat loss by a further 10–15% above the calculated value. A D500 wall 300 mm thick without insulation loses heat 2,5 times faster than the standard — in winter, heating such a house consumes 60–80% more energy than with a properly insulated facade.

The myth “a gas block does not need insulation” — why it is a misconception

The myth that aerated concrete heats on its own arose because of its porous structure and low thermal conductivity (0,12–0,18 W/(m·K)), but in practice even D400 500 mm thick falls short of modern thermal protection standards by 15–25%. Aerated concrete manufacturers such as Aeroc and H+H explicitly state in their technical documentation the need for external insulation for all regions with a design temperature below −15°C — Almaty falls into this zone with a margin. Homeowners who believed the myth discover dark spots of mould on the inner corners of walls and window reveals after 2–3 years: moisture that cannot escape through the vapour-tight layer condenses inside the block. Ignoring the manufacturer's recommendation leads to freezing of the walls, mould in the corners and higher heating bills by 40–60% —, while a major facade repair with dismantling of the finish costs 2–3 times more than timely insulation.

Why insulation vapour permeability is critical for gas block

Vapour permeability of insulation for aerated concrete — insulation layers on an aerated concrete wall, what to insulate aerated concrete with on the outside

Insulation for aerated concrete is a common question, so we will examine it in detail. Aerated concrete “breathes” — it lets water vapour out. If the insulation blocks this process, condensate forms inside the wall. We break down the physics of the process.

What “aerated concrete breathes” means and why it matters

The vapour permeability of aerated concrete is 0,14–0,23 mg/(m·h·Pa) — this means that water vapour from the room freely passes through the wall to the outside, preventing moisture accumulation inside the material. The cellular structure of aerated concrete contains millions of open pores 0,5–1,5 mm in diameter — it is these that ensure vapour diffusion without capillary suction of water. In winter, when indoor humidity is 50–60% (after cooking, showering, breathing) and outside the air is dry and frosty, the vapour pressure gradient draws moisture out of the wall. If the vapour outlet is blocked by vapour-tight insulation, the humidity in the aerated concrete reaches 80–90% — in winter, and when water freezes it expands by 9%, which over 3–5 seasons leads to microcracks and gradual destruction of the masonry.

Dew point — its shift when insulating aerated concrete

The dew point is the temperature at which water vapour in the air turns into condensate; with proper insulation using a vapour-permeable material, the dew point shifts out of the thickness of the aerated concrete into the insulation, where the condensate safely evaporates. In an uninsulated wall in winter, the dew point is inside the aerated concrete at a depth of 5–15 cm from the outer surface — that is exactly where moisture condenses and freezes. When we install a layer of mineral wool 100 mm thick on the outside, the condensation zone shifts into the insulation, where the vapour is vented outside through ventilation. When insulating with polystyrene foam, the dew point remains inside the aerated concrete or at the “aerated concrete–polystyrene” boundary — in winter the condensate freezes, and each freeze-thaw cycle reduces the strength of the aerated concrete by 5–10%.

Vapour permeability of different insulation materials compared with gas block

InsulationVapour permeability, mg/(m·h·Pa)Suitable for gas blockCause
Mineral wool0,3–0,6YesHigher than aerated concrete — vapour escapes outwards
Cellulose insulation0,4–0,6YesVapour-permeable, eco-friendly
Polystyrene foam (PSB-S)0,03–0,05No10–15 times lower than aerated concrete — condensation
Extruded polystyrene foam0,005–0,02NoAlmost vapour-tight — risk of destruction
Polyurethane foam (PUF)0,02–0,05With reservationsRequires precise dew point calculation

The difference in vapour permeability between mineral wool and polystyrene is 10–15 times, which makes polystyrene and penoplex fundamentally unsuitable for aerated concrete without special engineering solutions.

What to insulate aerated concrete with outside — mineral wool, polystyrene and alternatives

Choosing insulation for aerated concrete — mineral wool and polystyrene side by side on a construction site, insulation for aerated concrete

Choosing insulation for aerated concrete is not a question of price but of construction physics. Let us compare mineral wool, polystyrene, eco-wool and PU foam by the critical parameters that determine the durability of the facade.

Mineral wool for a gas block — why it is the optimal choice

Mineral wool is the only insulation whose vapour permeability (0,3–0,6 mg/(m·h·Pa)) is higher than that of aerated concrete (0,14–0,23 mg/(m·h·Pa)), which ensures unimpeded vapour escape and eliminates the risk of condensation in the wall. In Almaty winters with frequent crossings through zero this is especially important: with daily fluctuations from −10°C during the day to −25°C at night, vapour actively migrates from the warm room to the outside, and any barrier in its path turns moisture into ice that expands the pores of the aerated concrete. The fibres of stone wool with a density of 100–150 kg/m³ are arranged chaotically, retaining air while letting vapour through — this is exactly the density needed for a wet facade system with subsequent plastering, whereas boards of 35–80 kg/m³ shrink over time, forming voids and thermal bridges (at a site in the Aksai-2 district, after 5 years the mineral wool sagged by 3–5 cm, which required complete dismantling of the facade). For facade insulation, choose stone wool boards with a density of 100–150 kg/m³ — they do not shrink and retain rigidity during installation, which is critical for a wet facade system under Almaty's temperature fluctuations.

Can a gas block be insulated with styrofoam — risks and consequences

Insulating aerated concrete with polystyrene foam shifts the dew point inside the wall — in winter the condensate freezes, and within 3–5 seasons the aerated concrete begins to break down with microcracks, while mould appears on the interior surfaces. The vapour permeability of expanded polystyrene (0,03–0,05 mg/(m·h·Pa)) is 4–6 times lower than that of aerated concrete, so moisture striving to escape hits an impermeable layer and accumulates at the “aerated concrete–polystyrene” boundary: with a wall thickness of 300 mm of grade D400, the dew point at −20°C outside and +22°C inside shifts 5–7 cm deeper — that is exactly where ice forms in winter, expanding the pores of the material. After 4 years, at one of the sites, a damp lower layer of aerated concrete was found under the polystyrene foam, along with black spots of fungus on the interior wall — dismantling the polystyrene and replacing the damaged blocks cost more than insulating with mineral wool in the first place. Polystyrene foam is acceptable only when the aerated concrete is at least 400 mm thick of grade D600 and provided the dew point remains within the polystyrene — but even then the service life of the facade is reduced by 10–15 years compared with mineral wool, and the risk of mould remains higher.

Eco-wool and PU foam — alternative insulation options

Ecowool (cellulose insulation) has a vapour permeability of 0,4–0,6 mg/(m·h·Pa) and is suitable for aerated concrete, but it requires special spraying equipment and protection against settling in vertical structures. When applied wet, ecowool fills all gaps without voids, forming a seamless layer — an advantage over mineral wool slabs, where the joints require sealing; however, in Almaty there are only a handful of contractors with certified equipment, and with dry blowing into vertical cavities, settling of up to 3–5 of the volume is possible after 10–15% years. PU (polyurethane foam) with a vapour permeability of 0,02–0,05 mg/(m·h·Pa) is close to polystyrene foam — its use for aerated concrete is possible only with an accurate calculation of the dew point and a layer thickness that excludes condensate in the wall, which in practice requires engaging a heating engineer and makes the project 40–60% more expensive compared with mineral wool.

Comparison of insulation materials for aerated concrete — summary table

ParameterMineral woolPSB-S polystyrene foamCellulose insulationPUR
Vapour permeability, mg/(m·h·Pa)0,3–0,60,03–0,050,4–0,60,02–0,05
Thermal conductivity, W/(m·K)0,035–0,0420,037–0,0430,038–0,0450,028–0,035
Density for facade, kg/m³100–15025–3550–70 (spray application)30–60
FlammabilityNG (non-combustible)G3–G4G2G2–G3
Service life, years40–5025–3030–4025–35
Compatibility with gas blockYesNo (risk)YesWith reservations

Aerated concrete insulation technology — wet and ventilated facade

Aerated concrete insulation technology — a wet facade with mesh and plaster, how to insulate an aerated concrete house

There are two main technologies for insulating aerated concrete — the wet facade and the ventilated facade. We look at how they differ, which wall build-up is correct and how to install it.

Wet facade for a gas block — step-by-step technology

A wet facade for aerated concrete is installed in five layers: priming the walls, adhesive fixing of the insulation with adhesive foam, mechanical fastening with disc anchors (5–6 pcs/m²), reinforcing with alkali-resistant fibreglass mesh in the base plaster layer, and finishing decorative plaster. The first stage is dust removal and deep-penetration priming, which reduces the absorbency of the aerated concrete (down to 0,23 mg/(m·h·Pa)) and evens out adhesion. Then mineral wool or EPS boards are set on adhesive foam applied in strips around the perimeter and in spots in the centre — this compensates for wall unevenness of up to 3 mm. After 24 hours, disc dowels 120–160 mm long with an expansion core are driven in; the head is recessed into the insulation by 1–2 mm so as not to interfere with the plaster layer. On top, a base plaster layer of 3–5 mm is applied, into which facade fibreglass mesh with a 5×5 mm cell is embedded, and after drying, decorative plaster such as bark beetle or pebble is applied. Adhesive foam is applied in strips around the perimeter of the board and in spots in the centre — this compensates for wall unevenness and ensures contact without voids where condensation could accumulate.

Ventilated facade for aerated concrete — construction and features

A ventilated facade for aerated concrete consists of a batten system (wooden or metal), a layer of insulation, a windproof membrane, a counter-batten for a ventilation gap of 40–60 mm and the final cladding (siding, porcelain stoneware, fibre cement panels). First, brackets are fixed to the aerated concrete with anchors, onto which the batten system is mounted from galvanised profile or 50×50 mm timber treated with preservative. Mineral wool slabs 100–150 mm thick are fitted friction-tight between the uprights (for Almaty conditions 100 mm at a density of 35–45 kg/m³ is sufficient), secured with disc dowels. A windproof vapour-permeable membrane (Tyvek or Izospan AM) is stretched over the insulation — it lets vapour out of the wall but does not let moisture in from outside. Then a counter-batten 40–60 mm thick is nailed on, creating a gap between the membrane and the cladding, and the finishing material is installed. The ventilation gap is essential — it removes moisture that penetrates into the insulation and prevents the aerated concrete from getting wet; without the gap the ventilated facade loses its purpose and performs worse than a wet one.

Fixing insulation to a gas block — adhesive or dowels

The insulation is attached to the aerated concrete using a combined method: first with adhesive foam (ensuring contact without voids), and after it dries — with umbrella dowels (5–6 pieces per 600×1200 mm slab) for mechanical fixing. The adhesive foam is applied in a strip around the perimeter of the slab at a distance of 3–5 cm from the edge and in two or three “blobs” in the centre — this pattern guarantees contact over the entire surface without air pockets. The umbrella dowels with a metal or plastic pin are driven in after the adhesive has cured (after a day) at the corners and in the centre of the slab, with the head sunk 1–2 mm. Using only dowels without adhesive is a mistake: air pockets remain between the insulation and the aerated concrete, where condensate forms; using only adhesive without dowels risks the slabs being torn off under wind loads.

Do you need to prime a gas block before insulating

Priming the aerated concrete before insulation is mandatory — it strengthens the surface layer, reduces absorbency (aerated concrete absorbs moisture like a sponge) and improves the adhesion of the adhesive foam to the base. For aerated concrete, only a deep-penetrating primer on an acrylate-silicone base with pH 7–8 — is suitable: it penetrates into the pores to a depth of 3–5 mm, binds dust and does not form a film on the surface. It is applied with a roller or sprayer in one coat, consumption — 150–200 ml/m²; after drying (2–4 hours at +20°C) the wall is ready for insulation installation. An ordinary acrylic primer can create a film on the surface that will worsen the vapour permeability of the wall and negate the advantages of mineral wool.

Comparison of wet and ventilated facades for aerated concrete

ParameterWet facadeVentilated facade
Layer compositionPrimer, adhesive foam, insulation, dowels, fibreglass mesh, plasterBattens, insulation, wind protection, counter-battens, cladding
Cost per m²2500–4000 Kzt4000–7000 Kzt
Service life before repair15–20 years30–50 years
RepairabilityDifficult (replastering the entire facade)Easy (individual panels can be replaced)
Resistance to mechanical damageLow (plaster is vulnerable to impacts)High (durable cladding)
Suitable for gas blockYesYes (optimal)

For aerated concrete in a climate with frequent crossings through 0°C (as in Almaty), a ventilated facade is preferable — it prevents moisture accumulation in the insulation during freeze-thaw cycles.

What insulation thickness is needed for a gas block — calculation and standards

The thickness of insulation is not “by eye” but by calculation. We break down what it depends on and which values are relevant for the southern and northern regions of Kazakhstan.

What the insulation thickness for a gas block depends on

The thickness of insulation for aerated concrete depends on three parameters: the thermal conductivity of the insulation (0,03–0,045 W/(m·K)), the thickness and grade of the aerated concrete itself (D400–D600), and the climatic zone — the colder the region, the thicker the layer. For a D500 block with a thickness of 300 mm, the thermal conductivity is about 0,14 W/(m·K), and its own thermal resistance is only 2,14 m²·°C/W against a norm of 3,5 for Almaty: the difference of 1,36 m²·°C/W is covered by the insulation, which at λ=0,04 W/(m·K) for mineral wool gives 54 mm according to SP 50.13330. If the wall is thinner than 300 mm or the aerated concrete grade is low (D400), the insulation thickness rises to 200 mm — and saving on the block turns into overspending on insulation; moreover, for Astana with a norm of 3,7 m²·°C/W and a design temperature of −35°C, the mineral wool layer reaches 150–180 mm versus 120–150 mm for Almaty's −22°C.

Calculating insulation thickness — formula and example

The insulation thickness is calculated using the formula: R = d/λ, where R is the required thermal resistance (for Almaty 3,5 m²·°C/W), d is the layer thickness in metres, and λ is the thermal conductivity of the material; for mineral wool with λ=0,04 W/(m·K), with a 300 mm wall of D500 (R=0,3/0,14=2,14), an additional resistance of 1,36 m²·°C/W is required, which gives a thickness of 1,36×0,04=0,054 m = 54 mm. However, this “bare” calculation according to SP 50.13330 does not take into account that the real thermal conductivity of aerated concrete in a wall is 10–15% higher than the laboratory value due to moisture, mortar joints and reinforced ring beams — in our practice the difference between the calculated 50–60 mm and the 100–150 mm that actually perform is common, especially on northern facades where insolation is minimal. In practice, 20–30% is added to the calculated thickness as a margin — for Almaty residents this gives 100–150 mm of mineral wool, since the formula does not account for cold bridges in the dowels, gaps between the slabs and real operating conditions.

Recommended insulation thickness for different regions and walls

RegionDesign temperature, °CWall thickness 300 mm (D500)Wall thickness 400 mm (D500)
Shymkent-1580–100 mm50–70 mm
Almaty-22120–150 mm80–100 mm
Astana-35150–180 mm120–150 mm

For Almaty houses with D500 aerated concrete 300 mm thick, 120–150 mm of mineral wool is required, while with a 400 mm wall the layer is reduced to 80–100 mm — but you cannot abandon insulation altogether, since even 400 mm does not provide the standard heat transfer resistance, and the dew point shifts inside the wall. For residents of the southern regions (Shymkent, Turkestan), 50–100 mm is enough, but at higher humidity (70–80%) it is worth taking the upper end of the range — otherwise condensation in the pores of the aerated concrete will destroy the block structure within 3–5 seasons.

Typical mistakes when insulating aerated concrete and how to avoid them

We look at the five most common mistakes when insulating aerated concrete — from choosing vapour-tight insulation to incorrect fastening — and explain how to avoid them.

Mistake 1 — insulating aerated concrete with polystyrene foam without a ventilation gap

Insulating aerated concrete with polystyrene foam without a ventilation gap leads to moisture accumulation inside the wall: the vapour permeability of polystyrene foam (0,05 mg/(m·h·Pa)) is 10 times lower than that of D500 (0,14 aerated concrete mg/(m·h·Pa)), so water vapour from the room does not escape outside and, at sub-zero temperatures, freezes at the block–insulation boundary. During a freeze-thaw cycle, the volume of water expands by 9%, creating internal pressure that destroys the cellular structure — after 2–3 winters, cracks and peeling plaster appear on the walls, especially in corner rooms. Owners of houses in Aksai and Alatau who saved on mineral wool see condensation zones across the entire facade area on a thermal imager after just two seasons, along with mould on the interior walls. If you nevertheless choose polystyrene foam, the only way to avoid destruction is to leave a ventilation gap of 40–60 mm between the insulation and the facade, but this complicates the structure and increases the cost; it is easier to take mineral wool with a vapour permeability of 0,3–0,6 mg/(m·h·Pa) straight away.

Mistake 2 — incorrect calculation of insulation thickness

The most common mistake is laying insulation 50 mm thick by eye: for the Almaty climate, with a 300 mm wall of D500, this will cover only 30–40% of the SP 50.13330 standard, and in winter the heating bill will grow 1,5–2 times. Owners often rely on the advice of market sellers offering standard 50 mm for any region — without taking into account that for fluctuations from –25°C in winter to +35°C in summer, a design heat transfer resistance of at least 3,0 m²·°C/W is required, and for 300 mm walls of D500 this means mineral wool 100–120 mm thick. Use online heat loss calculators or the formula from SP 50.13330 —: they take into account the region, wall thickness and type of insulation; saving 10 000 KZT on thickness will turn into 50 000 KZT of overpayment for heating over the winter.

Mistake 3 — thermal bridges through fixings and joints

Metal dowels used to fix the insulation create thermal bridges: each steel dowel 10 mm in diameter reduces insulation efficiency by 5–10%, and at a density of 6–8 pcs/m² the total heat loss through the fasteners reaches 15–20% of the calculated value — this is equivalent to having no insulation over an area of 1,5–2 m² for every 10 m² of facade. In winter, condensation forms in these areas, runs down and moistens the lower courses of the aerated concrete, causing local freezing and peeling of the plaster. Unsealed joints between insulation boards are especially critical — through gaps of 2–3 mm heat loss increases by a further 10–15%, and on a thermal imager such walls look like a grid of dark stripes. Use plastic disc dowels with a thermal break — they conduct 3–4 times less cold than metal ones; also be sure to seal the joints between insulation boards with tape or mounting foam.

Mistake 4 — insulating wet or not-yet-dry aerated concrete

Aerated concrete can only be insulated after the masonry has fully dried — 3–6 months after the walls are erected; the moisture content of fresh aerated concrete reaches 30–40%, and if it is covered with insulation, the moisture remains inside, leading to mould and a reduction in the strength of the blocks by 20–30%. In Almaty's autumn with frequent rains, the drying process drags on: at an average temperature of +10 °C, aerated concrete loses only 3–5% of moisture per month, so a house built in August may only be ready for insulation by March. Owners who insulated their walls a month after laying found black fungus under the insulation just a year later, and the blocks crumbled when they tried to dismantle it. Check the moisture content of the aerated concrete with a moisture meter — the acceptable value before insulation is no more than 10–12%; in the rainy season, drying can take up to 8–10 months.

Mistake 5 — no vapour barrier on the interior side

Without a vapour barrier on the inner side of the walls, water vapour from the room (from cooking, showering, breathing) penetrates into the aerated concrete, reaches the insulation and condenses there — at sub-zero temperatures the water freezes and destroys both the block and the insulation. In a day, a family of 4 people releases 10–12 litres of water vapour, and if the wall is not protected from the inside, all the moisture goes into the aerated concrete, and in winter into the insulation, where, with a temperature difference from +20 °C inside to –20 °C outside, condensation forms in a volume of up to 0,5 litres per square metre. In houses with gas heating this problem is compounded by a sharp humidity difference: in winter indoor humidity reaches 60–70%, while outside it is 30–40%, and the vapour pressure gradient pushes moisture into the wall. Install a vapour barrier film with a vapour permeability of no more than 0,01 mg/(m·h·Pa) on the inner side of the walls, and seal all joints with special tape — this is cheaper and easier than repairing frozen walls after 2–3 years.

Conclusion

Insulating aerated concrete is not an option but a mandatory stage of construction in Almaty's climate. We have compiled five key takeaways that will help you avoid costly mistakes.

Key takeaways

  • Aerated concrete must be insulated — even a 400 mm wall of D500 does not provide the standard thermal resistance for the climate of Almaty and Astana.
  • Choose vapour-permeable insulation — mineral wool with a density of 35–50 kg/m³ is safe for aerated concrete, while polystyrene without a ventilation gap destroys the walls.
  • The insulation thickness is calculated according to SP 50.13330 —; for Almaty with a 300 mm wall you need 120–150 mm of mineral wool, for Astana — 150–180 mm.
  • The insulation technology includes three layers — insulation, wind protection, ventilation gap and finishing cladding; skipping any stage reduces efficiency.
  • Avoid typical mistakes — do not insulate damp aerated concrete, do not use metal fasteners without a thermal break, and do not forget about the vapour barrier on the inside.

About the author

Arman Zhumabekov

A specialist in insulating and finishing aerated concrete. Works with the PROFI-DOM workshop in Almaty.

Insulating aerated concrete houses: vapour permeability, mineral wool, plaster, dew point.

Phone:+7 (777) 327-97-34Our address:Almaty, Makataev St., 47, office 325 (Partner Business Centre)Daily: 9:00–21:00 (by appointment)